Question: 15-16 Using the information in Chapter 12, problem 12-18 complete table 15-17 Project Planning Budget: Weeks After Go-Ahead Problem 12-18 Activity 1 2 3 4
15-16 Using the information in Chapter 12, problem 12-18 complete table 15-17
Project Planning Budget: Weeks After Go-Ahead
Problem 12-18
| Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | Total $ |
| AB | 2,000 | 2,000 | 2,000 | 6,000 | |||||
| AC | 3,000 | 4,000 | 4,000 | 4,000 | 5,000 | 20,000 | |||
| AD | 2,000 | 3,000 | 2,500 | 7,500 | |||||
| BF | 2,000 | 3,000 | 4,000 | 3,000 | 3,000 | 15,000 | |||
| CE | 2,500 | 2,500 | |||||||
| DE | 3,500 | 3,500 | 3,500 | 10,500 | |||||
| EF | 3,000 | 3,000 | |||||||
| TOTAL | 7000 | 9000 | 8500 | 9500 | 11,500 | 10,000 | 6,000 | 3000 | 64,500 |
Table 15-17 Project Cost
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Activity | Percent Complete | Budgeted Cost for Work Scheduled | Budgeted Cost for Work Performed | Actual Cost for Work Performed | CostVariance=4-5 | Schedule Variance= 4-3 |
| Total |
Cost variance ($)- column4-column 5=
Schedule variance ($)= Column 4-Column 3=
Time-to-Complete=
Cost-at-Completion=rate of spending x Total budget=Column 5/Column 4 x ( )=
Cost-to-complete= (cost-at-completion)-ACWP=