Question: 15-16 Using the information in Chapter 12, problem 12-18 complete table 15-17 Project Planning Budget: Weeks After Go-Ahead Problem 12-18 Activity 1 2 3 4

15-16 Using the information in Chapter 12, problem 12-18 complete table 15-17

Project Planning Budget: Weeks After Go-Ahead

Problem 12-18

Activity 1 2 3 4 5 6 7 8 Total $
AB 2,000 2,000 2,000 6,000
AC 3,000 4,000 4,000 4,000 5,000 20,000
AD 2,000 3,000 2,500 7,500
BF 2,000 3,000 4,000 3,000 3,000 15,000
CE 2,500 2,500
DE 3,500 3,500 3,500 10,500
EF 3,000 3,000
TOTAL 7000 9000 8500 9500 11,500 10,000 6,000 3000 64,500

Table 15-17 Project Cost

1 2 3 4 5 6 7
Activity Percent Complete Budgeted Cost for Work Scheduled Budgeted Cost for Work Performed Actual Cost for Work Performed CostVariance=4-5

Schedule Variance=

4-3

Total

Cost variance ($)- column4-column 5=

Schedule variance ($)= Column 4-Column 3=

Time-to-Complete=

Cost-at-Completion=rate of spending x Total budget=Column 5/Column 4 x ( )=

Cost-to-complete= (cost-at-completion)-ACWP=

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!