Question: 1.A project was estimated at 352 Function points. A four-person team will be assigned to this project consisting of an architect, two programmers, and a
1.A project was estimated at 352 Function points. A four-person team will be assigned to this project consisting of an architect, two programmers, and a tester. The charge labor rate of the architect is $8,000 per month, the programmers $6,000 and the tester $5,000. The average productivity for the team is 8 FP per person month. Which of the following represents the projected cost of the project?
| $275,000 | ||
| $281,600 | ||
| $209,000 | ||
| $269,500 |
2.A company needs to develop a digital signal processing software for one of its newest inventions. the software is expected to have 40000 lines of code. The company needs to determine the effort in person-months needed to develop this software using the basic COCOMO model. The multiplicative factor for this model is given as 2.8 for the software development on embedded systems, while the exponentiation factor is given as 1.20. What is the estimated effort in person-months?
| 234.25 | ||
| 932.50 | ||
| 287.80 | ||
| 122.40 |