Question: A Software project was estimated at 432 Function Points. A six-person team will be assigned to project consisting of a system analyst, one designer, two
A Software project was estimated at 432 Function Points. A six-person team will be assigned to project consisting of a system analyst, one designer, two programmers and two testers. The salary of the designer is SR7000 per month, system analyst is SR5000 per month, programmer is SR6000 per month and a tester is SR6000 per month. Average productivity for the team is 12 FP per person month.
25. What is the estimated project duration? A. 6 months B. 12 months C. 36 months D. 72 months
26. Which of the following represents the projected cost of the project?
A. SR 24.000
B. SR 36 000
C. SR 144 000
D. SR 216 000 27.
If the project must be complete in three months, how many people will be needed for the project?
A. 144 B. 72 C. 36 D. 12
14. Which of the following is not among the reason(s) why project managers need to understand their ganization's mission and strategy? A- To make appropriate decisions and adjustments B-To be effective project advocates G C- To be able to get their day to day work D. None of the answers is correct
4. In project selection, applying a strategic goals. to bring projects to closer with the organization's
A. weighted scoring model
B. net present value method
C. internal rate of return
D. payback method