Question: 1b. A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95%, and workday allowance

1b. A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95%, and workday allowance is 10%. Determine each of the following: a. Observed time. b. Normal time. c. Standard time