A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The

Question:

A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95 percent, and workday allowance is 10 percent. Determine each of the following:

a. Observed time.

b. Normal time.

c. Standard time.