Question: A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95 percent, and workday allowance
A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95 percent, and workday allowance is 10 percent. Determine each of the following:
a. Observed time.
b. Normal time.
c. Standard time.
Step by Step Solution
3.37 Rating (187 Votes )
There are 3 Steps involved in it
OT 12 minutes PR 95 A 10 of wo... View full answer