Question: 1.Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly line balancing. She has been told that the firm needs to complete
1.Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly line balancing. She has been told that the firm needs to complete 96 instruments per 24-hour day. The assembly-line tasks for the production of the instrument are shown in the image.

Task Time (minutes) Predecessors A A, B B C F D. E H E G, I, J a. Draw the precedence diagram (untea) Precedence Graph . POM for Windows - [Data] Results DOX (untitled) Solution Early Early Late Late Activity Activity Slack time Start Finish Start Finish Project 23 A 0 3 0 3 0 B 6 6 O 6 0 0 C 7 3 10 3 10 0 D 5 6 11 6 11 0 F 6 8 9 11 F 4 10 14 10 14 0 G 19 14 19 H 18 11 18 14 13 19 K 19 23 19 23