Question: Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly line balancing. She has been told that the firm needs to complete
Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly line balancing. She has been told that the firm needs to complete 96 instruments per 24-hour day. The assembly-line activities are

- a) Draw the precedence diagram. (4p)
- b) What is the cycle time? (4p)
- c) What is the theoretical minimum number of work stations? (4p)
- d) Assign tasks to workstations. (4p)
- e) How much the total idle time? (2p)
- f) What is the overall efficiency of the assembly line? (2p)