Question: 1)Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the

1)Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the forward pass and backward pass methods and complete Table 1(b).

2)Draw a resource profile (histogram) with a maximum of eight (8) labourers per day.

Also, improve the daily resource use (start low, increase the resource use gradually till it peaks around the middle of the project, then gradually decrease it towards the end of the project). Give your comments on the overall resource profile.

 1)Draw the Critical Path Method (CPM) network diagram and highlight the

Tahle 1(a) / Jadual 1(a) *Immediately Preceding Activities / Aktiviti Mendahului Serta-merta Table 1(b) / Jadual 1(b)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!