Question: 1.________occurs when the activities in a stage of a process must stop because there is no work Select one a Pacing b. Starving C Buffering
1.________occurs when the activities in a stage of a process must stop because there is no work
Select one
a Pacing
b. Starving
C Buffering
d. Setup
2.Enablers drive the overall performance of the Supply Chain Management (SCM) system which of the following is not an SCM enabler
Select one:
A Worker Compensation and benefits
B. Measurement
c Design
d. Periodic Review
3.In respect of Project Evaluation and Review Technique (PERT), the maximum time required to complete an activity is known as ---
Select one:
O a. Most likely time
O b. Pessimistic time
O c. Optimistic time
O d. Expected time
4.Annual demand = 18,000 units. EOQ = 1,000 units. The total number of orders per year = orders
Select one:
a. 16
b.18
C. 20
d. 22
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts