Question: Consider the following information about a small project: Task Duration ( days ) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A 5 None

Consider the following information about a small project:
Task
Duration (days)
Immediate Predecessors
Shortest Time Possible
Acceleration Cost per day
A
5
None
4
$6,500
B
10
A
9
$5,000
C
8
A
7
$7,000
D
6
B
3
$6,000
E
7
C
6
$6,000
F
3
C
2
$7,000
G
4
D,E,F Question 6 What is the critical path by forward and backward paths? (Only put letters, do not leave space in your answers. For example, if your answer is A to C to E and to G, put down ACEG in the blank.)
ANSWER :ABDG (CORRECT ANSWER) Question 7 The duration of the project is ____ days. (Integer answer, only put numbers, do not put anything else)
ANSWER : 25(CORRECT ANSWER) Question 8 For the tasks that are not on the critical path, task ____ has the longest slack. (Only put letters, do not put anything else)
ANSWER : C (WRONG ANSWER) Question 9 Following the previous question, the task with the longest slack has a slack of ____ days. (Integer answer, only put numbers, do not put anything else)
ANSWER : 2(WRONG ANSWER) I wrote the wrong questions, can you solve them again?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!