Question: Consider the following information about a small project: Task Duration ( days ) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A 5 None
Consider the following information about a small project:
Task
Duration days
Immediate Predecessors
Shortest Time Possible
Acceleration Cost per day
A
None
$
B
A
$
C
A
$
D
B
$
E
C
$
F
C
$
G
DEF Question What is the critical path by forward and backward paths? Only put letters, do not leave space in your answers. For example, if your answer is A to C to E and to G put down ACEG in the blank.
ANSWER :ABDG CORRECT ANSWER Question The duration of the project is days. Integer answer, only put numbers, do not put anything else
ANSWER : CORRECT ANSWER Question For the tasks that are not on the critical path, task has the longest slack. Only put letters, do not put anything else
ANSWER : C WRONG ANSWER Question Following the previous question, the task with the longest slack has a slack of days. Integer answer, only put numbers, do not put anything else
ANSWER : WRONG ANSWER I wrote the wrong questions, can you solve them again?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer