Question: Task Duration (days) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A 5 None 4 $6,500 B 10 A 9 $5,000 C 8 A
| Task | Duration (days) | Immediate Predecessors | Shortest Time Possible | Acceleration Cost per day |
| A | 5 | None | 4 | $6,500 |
| B | 10 | A | 9 | $5,000 |
| C | 8 | A | 7 | $7,000 |
| D | 6 | B | 3 | $6,000 |
| E | 7 | C | 6 | $6,000 |
| F | 3 | C | 2 | $7,000 |
| G | 4 | D,E,F |
What is the critical path by forward and backward paths? (Do not leave space in your answers. For example, if your answer is A to C to E and to G, put down ACEG in the blank.)
Question 7
The duration of the project is ____ days.
Question 8
For the tasks that are not on the critical path, task ____ has the longest slack.
Question 9
Following the previous question, the task with the longest slack has a slack of ____ days.