Question: 1.When considering the agile project management process, at the end of each iterationSingle choice. (1 Point) Team members are released to work on other projects
1.When considering the agile project management process, at the end of each iterationSingle choice.
(1 Point)
Team members are released to work on other projects
The Scrum master assigns daily tasks to team members
Product owner determines whether or not the project is complete
Stakeholders and customers review progress and re-evaluate priorities
2._____________ represents a fundamental shift away from the traditional plan-driven project management approach by adopting a more experimental and adaptive approach to managing projectsSingle choice.
(1 Point)
Agile project management
Hybrid project management
Uncertain project management
Focused project management
3.Traditional approaches to project management concentrate firmly onSingle choice.
(1 Point)
Thorough planning up front
New technology
Flexibility
Change
4.Project ________ varies according to the extent the project scope is known and stable and the technology to be used is known and provenSingle choice.
(1 Point)
Stability
Balance
Unity
Uncertainty
5.Iterative development processes provide the following important advantages EXCEPTSingle choice.
(1 Point)
Continuous integration of the evolving product
Ease of comparing actual information against planned
Frequent demonstration of progress to increase the likelihood that the end product will satisfy customer needs
Early detection of defects and problems