Question: 1.You have determined the following for a given project: Expected completion time of the project = 26 weeks Standard deviation of project completion time =
1.You have determined the following for a given project:
Expected completion time of the project = 26 weeks
Standard deviation of project completion time = 8
What is the probability of completing the project in more than 32 weeks?
Report your answer as a decimal and take it to four places.
2.
Using the chart of activity data provided below, what is expected standard deviation for activity C?
| Activity | Optimistic | Most Likely | Pessimistic |
| A | 9 | 12 | 21 |
| B | 14 | 21 | 23 |
| C | 10 | 15 | 25 |