Question: 2 0 2 4 Summer ( 1 4 pts ) A project has the activity duration and cost information indicated in the table. table
Summer
pts A project has the activity duration and cost information indicated in the table.
tableActivitytableNormalDuration monthstableNormalCost tableCrashDuration monthstableCrashCost tableImmediatePredecessorsANoneBNoneCA BDA BECFEGD
a Draw the activityorsode network diagram and find the project completion time and the
critical path.
b pts Which activity or activities should be crashed to complete the project I month before its current completion time?
c Which activities should be crashed and by how much each activity should be crashed to complete the project in months? How much would the total cost increase?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
