Question: 2 0 2 4 Summer ( 1 4 pts ) A project has the activity duration and cost information indicated in the table. table

2024 Summer
(14 pts) A project has the activity duration and cost information indicated in the table.
\table[[Activity,\table[[Normal],[Duration (months)]],\table[[Normal],[Cost (5)]],\table[[Crash],[Duration (months)]],\table[[Crash],[Cost (5)]],\table[[Immediate],[Predecessor(s)]]],[A,3,290,2,250,None],[B,4,500,2,700,None],[C,5,600,4,800,A, B],[D,3,1000,2,1500,A, B],[E,2,350,1,600,C],[F,4,400,2,1000,E],[G,6,100,4,200,D]]
a.(6pts) Draw the activity-or-sode network diagram and find the project completion time and the
critical path.
b.2 pts) Which activity (or activities) should be crashed to complete the project I month before its current completion time?
c.(6pts) Which activities should be crashed and by how much each activity should be crashed to complete the project in 12 months? How much would the total cost increase?
2 0 2 4 Summer ( 1 4 pts ) A project has the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!