Question: [ 2 0 points ] A youth organization is planning a project to build a jungle gym for kids. The planning team has identified 1
points A youth organization is planning a project to build a jungle gym for kids. The planning team has identified activities, named AJ and activity times for the project. The tasks, durations in days costs, and predecessor relationships are shown as follows:
tableActivityImmediate Predecessor,Activity TimeANone,BNone,CA BDAEC DFDGCHE FIFJG I,
MGMT : Management Science and Operations Management
a Draw the network for this project. If you draw on a paper, scan and insert into the docx or pdf file. If images are uploaded separately, they will not be graded.
b Create the activity schedule and calculate ES EF LS and LF times. Activity schedule is a table with ES EF LS LF times for each activity.
c Calculate the slack for each activity. What do they mean?
d What are the critical path activities? Why are they important?
e What is the project completion time? Under what conditions is this project completion time valid?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock