Question: 2 . 3 Construct the network diagram ( Activity on Node AON ) . ( 1 5 ) ACTIVITY PREDECESSOR MOST OPTIMISTIC ( DAYS )

2.3 Construct the network diagram (Activity on Node AON).(15)
ACTIVITY PREDECESSOR MOST OPTIMISTIC
(DAYS)
MOST LIKELY
(DAYS)
MOST PESSIMISTIC
(DAYS)
A -6916
B A 111520
C A 2610
D B 101215
E B 256
F C 4612
G E;F 6914
H D;E 3711
I H;G 369