Question: 2 7 . When the demand for resources is greater than the available supply, the project manager can use a scheduling method that adjusts the

27. When the demand for resources is greater than the available supply, the project manager can use a scheduling method that adjusts the start and finish dates of activities in order to address resource limits or constraints. This technique is called: ___________:
A. Fast tracking
B. Crashing
C. Resource leveling
D. Critical path method