Question: 2 7 . When the demand for resources is greater than the available supply, the project manager can use a scheduling method that adjusts the
When the demand for resources is greater than the available supply, the project manager can use a scheduling method that adjusts the start and finish dates of activities in order to address resource limits or constraints. This technique is called: :
A Fast tracking
B Crashing
C Resource leveling
D Critical path method