Question: 2 . 8 3 . ( 1 2 . 3 4 ) You complete your PERT calculations for your project and you have determined your

2.83.(12.34)You complete your PERT calculations for your project and you have determined your expected duration is 49 weeks with a standard deviation ofYou want your project to complete on your end date with a 60% probability. How many weeks before your goal end date do you begin your project?