Question: Activity Preceding Optimistic (O) Probable (M) Pessimistic (P) Expected (E) Variance A - 7 9 14 9.5 1.361111 B A 2 2 8 3 1
Activity Preceding Optimistic (O) Probable (M) Pessimistic (P) Expected (E) Variance
A - 7 9 14 9.5 1.361111
B A 2 2 8 3 1
C A 8 12 16 12 1.777778
D - 3 5 10 5.5 1.361111
E C 4 6 8 6 0.444444
F B 6 8 10 8 0.444444
G F 2 3 4 3 0.111111
H D,E 2 2 8 3 1
I G 6 8 16 9 2.777778
J H 4 14 14 12.33333 2.777778
K I,J 2 5 5 4.5 0.25
a. Expected time for each activity = (O+4M+P)/6
Paths and expecteddurations:
A-B-F-G-I-K = 9.5+3+3+9+4.5 = 29
A-C-E-H-J-K = 9.5+12+6+3+12.3+4.5 = 47.3
D-H-J-K = 5.5+3+12.3+4.5 = 25.3
b. Critical path is A-C-E-H-J-K as the duration is highest.
c. Variance of each activity = ((P-O)/6)^2
Project variance = Sum of variances of activities on critical path i.e (A,C,E,H,J,K) = 1.36+1.78+0.44+1+2.78+0.25 = 7.61
d. Project Standard deviation = \sqrt{} Project Variance = \sqrt{} 7.61 = 2.76
what is the standard deviation of this exercise?
also what is the probability of completion of the project after week 40
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts