Question: 2. A project is using three time estimate to determine completion of the project. The project Te has been calculated to be 54 days. The

2.

A project is using three time estimate to determine completion of the project. The project Te has been calculated to be 54 days. The variance along critical path has been calculated to be 49 days. The customer has asked what the probability of the project taking 56.8 days or longer would be. What is this probability? Select one:

a. Between 34 and 35%

b. None of these answers are even remotely close to correct

c. Between 8.0 and 8.1%

d. 40%

e. Between 65 and 66%

3.

Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 7, 10, 10, 8, 8, and 20 minutes, and the cycle time is 20 minutes? Select one:

a. 2.15

b. 3

c. None of these answers are correct

d. 8

e. 3.15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!