Question: a) Create an AON network diagram for this project. b) Using PERT assumptions, calculate the individual expected times (Te) for each activity. c) Which tasks

a) Create an AON network diagram for thisa) Create an AON network diagram for this

a) Create an AON network diagram for this project.

b) Using PERT assumptions, calculate the individual expected times (Te) for each activity.

c) Which tasks are on the critical path, and what is the expected completion time for the project?

3) predecessor none Activity A B C optimistic 3 days 2 days 5 days 8 days 2 days most likely 4 days 2 days 6 days 10 days 4 days pessimistic 5 days 5 days 10 days 12 days 6 days none A and B A C E Potentially useful formulae: Standard deviation = V variance Z = target time finish time Standard deviation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!