6. A company wants to plan a project using PERT to modify one of their products which has poor sales. They have determined the following activities, precedence relationships and time estimates in weeks for the project:
Most
Immediate Optimistic Likely Pessimistic
Activity Predecessors to tm tp
a - 4 6 7
b a 1 2 3
c a 5 5 5
d b 7 9 12
e b 2 4 8
f c,d 6 9 10
a. Find the critical path.
b. What is the probability that the project will take longer than 28 weeks to complete?