Question: 2. Activity Nor. Time Predec. Crash time Crash cost Nor. cost A 4 - 3 FD 500FD 300 B 3 A 1 FD 325FD 250
2. Activity Nor. Time Predec. Crash time Crash cost Nor. cost
A 4 - 3 FD 500FD 300
B 3 A 1 FD 325FD 250
C 5 A,B 4 FD 550FD 400
D 6 B, C 3 FD 250FD 150
E 3 C,D 2 FD 200FD 300
And, possible crash cost and time for each activity;
Determine:
- Crash cost per week for each activity
Which activities should be crashed to meet a project deadline of 13 weeks at minimum cost. Assume partial crash is allowed.