Question: + 2 AD Read aloud V Draw Highlight QUESTION 4 [23] 4. The following costs have been estimated for the activities in a project: ACTIVITY

+ 2 AD Read aloud V Draw Highlight QUESTION 4 [23] 4. The following costs have been estimated for the activities in a project: ACTIVITY IMMEDIATE PREDECESSORS TIME (DAYS) COST (RAND) A B. D E F G A B C D CD F 8 4. 3 5 6 5 3 8000 12000 6000 15000 9000 10000 6000 a. Determine the critical path of the project. (7) b. Develop a cost schedule based on earliest start times. (8) c. Develop a cost schedule based on latest start times. (8)