Question: 2 . Answer Questions ( 2 mathrm { a } - 2 mathrm { c } ) using the figure shown

2. Answer Questions \(2\mathrm{a}-2\mathrm{c}\) using the figure shown below: (21 points)
2a. The critical path is and its length is weeks.
2b. The total slack time in Activity "F" is weeks
2c. If the crash cost/week for all activities is the same and we can crash all activities by 2 weeks except Activity H by a week and customer wants us to shorten the project length by 3 weeks, we should crash Activity by week(s) first and then crash Activity by week(s).