Question: 2. Consider a project having the following seven activities: Normal Normal Crash Crash Maximum Immediate Time Cost Time Cost Weeks Activity Predecessors (weeks) ($) (weeks)

2. Consider a project having the following seven activities:

Normal Normal Crash Crash Maximum

Immediate Time Cost Time Cost Weeks

Activity Predecessors (weeks) ($) (weeks) ($) Reduced

A none 4 3,000 3 6,000 1

B none 3 5,000 2 7,000 1

C A 9 2,000 7 4,000 2

D A, B 2 3,000 2 3,000 0

E B 9 4,000 6 7,000 3

F C, D 8 4,000 6 9,000 2

G E, F 5 2,000 3 5,000 2

(a) What is the expected project completion time? (3pts)

(b) What is the critical path? (3pts

(c) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? (4pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!