Question: 2 . Create a resource loading table and perform resource leveling on the project composed of the activities in this table. You may use Excel
Create a resource loading table and perform resource leveling on the project composed of the
activities in this table. You may use Excel for your convenience.
Activity Duration
days
Amount of
hoursday Total hours Predecessor
A
B
C A
D B
E C D
F E
G E
H F
I F
J G H I
K J
L K
a Construct the project network diagram.
b Identify the ES EF LS LF float and the critical path.
c Create a TimePhased Resource Loading Table for this project, identifying the activity early
start and late finish points in the table
d Assume that the maximum amount of time used per day is hours. With this resources
usage limitations can you identify any weeks with resource over commitments?
e Resource level the loading table. Identify the activity that can be rescheduled and
reconfigure the table to show this reallocation.Create a resource loading table and perform resource leveling on the project composed of the activities in this table. You may use Excel for your convenience.
tableActivitytableDurationdaystableAmount ofhoursdayTotal hours,PredecessorABCADBEC DFEGEHFIFJG H IKJLK
a Construct the project network diagram.
b Identify the ES EF LS LF float and the critical path.
c Create a TimePhased Resource Loading Table for this project, identifying the activity early start and late finish points in the table
d Assume that the maximum amount of time used per day is hours. With this resource's usage limitations can you identify any weeks with resource over commitments?
e Resource level the loading table. Identify the activity that can be rescheduled and reconfigure the table to show this reallocation.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock