Question: 2 . Create a resource loading table and perform resource leveling on the project composed of the activities in this table. You may use Excel

2. Create a resource loading table and perform resource leveling on the project composed of the
activities in this table. You may use Excel for your convenience.
Activity Duration
(days)
Amount of
hours/day Total hours Predecessor
A 6636--
B 11010--
C 2816 A
D 41040 B
E 188 C, D
F 188 E
G 6848 E
H 3824 F
I 2816 F
J 3824 G, H, I
K 5840 J
L 3824 K
a) Construct the project network diagram.
b) Identify the ES, EF, LS, LF, float and the critical path.
c) Create a Time-Phased Resource Loading Table for this project, identifying the activity early
start and late finish points in the table
d) Assume that the maximum amount of time used per day is 16 hours. With this resources
usage limitations, can you identify any weeks with resource over commitments?
e) Resource level the loading table. Identify the activity that can be rescheduled and
reconfigure the table to show this reallocation.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!