Question: 2. Develop a crashing schedule [10 marks). (Replace the marks with 5). Activity Crash Time a Normal Time 7 5 Cost per day to crash

2. Develop a crashing schedule [10 marks).

2. Develop a crashing schedule [10 marks). (Replace the marks with 5). Activity Crash Time a Normal Time 7 5 Cost per day to crash $100 $200 b 2 6 C 6 8 . d $300 e 7 f 7 . $150 $500 G 3 1 Project costs are $650 per day. 7 3 a b 7 5 5 7 8