Question: 2. Develop a crashing schedule [8 marks). Activity Normal Time Crash Time Cost per day to Crash a 7 2 $ 500 b 5 3

2. Develop a crashing schedule [8 marks).

2. Develop a crashing schedule [8 marks). Activity Normal Time Crash Time Cost per day to Crash a 7 2 $ 500 b 5 3 $ 300 8 8 d 6 4 $ 400 e 3 1 $ 350 f 7 4 $ 100 g 3 1 $ 550 Project's Budget per day: $500 b e 5 3 a Start | 7 f 8 6 7