Question: 2. Earned Value (EV) for a new operating system design project is calculated at $300,000 and the Ac-tual Cost (AC) is $280,000. The Budget at
2. Earned Value (EV) for a new operating system design project is calculated at $300,000 and the Ac-tual Cost (AC) is $280,000. The Budget at Completion (BAC) is estimated at $500,000. The project is progressing well from a budgetary point of view, since the CPI value is greater than one. What is the Estimate at Completion (EAC) if the future work of the project is performed at the budg-eted rate?