Question: Earned Value ( EV ) for a new operating system design project is calculated at $ 3 0 0 , 0 0 0 and the
Earned Value EV for a new operating system design project is calculated at $ and the Actual Cost AC is $ The Budget at Completion BAC is estimated at $ The project is progressing well from a budgetary point of view, since the CPI value is greater than one.
What is the Estimate at Completion EAC if the future work of the project is performed at the
budgeted rate?