Question: 2. Find the critical path for the network activities shown below and determine its duration. Activity Duration Immediate Predecessors A 2 B 4 --

2. Find the critical path for the network activities shown below and

2. Find the critical path for the network activities shown below and determine its duration. Activity Duration Immediate Predecessors A 2 B 4 -- C 1 A,B D 6 A,B E 3. B,C,D