Question: The critical path for the network activities shown below is _ _ _ _ _ _ _ _ with duration _ _ _ _ _

The critical path for the network activities shown below is ________ with duration ________.
Activity Duration (Day) Immediate Predecessors
Q 2--
P 6--
Y 6 P, Q
X 1 P, Q
Z 2 Q, Y, X
Question 15 options:
P-Y-Z; 14 days
Q-Y-Z; 10 days
Q-P-Y-X-Z; 17 days
Q-X-Z; 5 days
P-X-Z; 9 days
Q-Z; 4 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!