Question: Question 46 (2 points) The critical path for the network activities shown below is with duration Activity Duration (Day) Immediate Predecessors A 4 B 2

Question 46 (2 points) The critical path for the

Question 46 (2 points) The critical path for the network activities shown below is with duration Activity Duration (Day) Immediate Predecessors A 4 B 2 A C 7 D 4 A E 5 B,C,D A-D-E; 13 days A-B-E; 11 days C-E; 12 days A-B-C-D-E; 22 days A-B-D; 10 days