Question: 2. Job times (including processing and set-up) are shown in the following table for five jobs waiting to be processed at a work center: JOB

2. Job times (including processing and set-up)

2. Job times (including processing and set-up) are shown in the following table for five jobs waiting to be processed at a work center: JOB JOB TIME DUE DATE A B D E 12 6 14 3 7 15 24 20 8 6 Determine the processing sequence that would result from each of these priority rules: a. FCFS b. SPT c. EDD d. LPT Compute for the following for each priority rule. Summarize on a table: Average Completion Time Utilization Average number of jobs in the system Average job lateness