Question: Job times (including processing and setup) are shown in the following table for five jobs waiting to be processed at a work center: Job Time

Job times (including processing and setup) are

Job times (including processing and setup) are shown in the following table for five jobs waiting to be processed at a work center: Job Time Due Date Job (hours) (hours) a 12 15 6 24 C 14 20 d 3 8 7 6 b e Determine the sequence of jobs, the average flow time, average tardiness, and average number of jobs at the work center for each of these priority rules: (a) SPT (Shortest processing time) (b) EDD, (Earliest due date) (c) FCFS, (First come first served)