Question: Assignment Processing times ( including setup times ) and due dates for six jobs waiting to be processed at a work center are given in

Assignment
Processing times (including setup times) and due dates for six jobs waiting to be processed at a work center are given in the following table.
\table[[Job,Processing Time (days),Due Date (days from present time)],[A,2,7],[B,8,15],[C,4,4],[D,11,17],[E,5,15],[F,12,18]]
a) Determine the sequence of jobs, the average completion time, average lateness, and average number of jobs at the work center, for each of these rules: FCFS, SPT, EDD, STR.
b) Compare the results of the rules.