Question: 2 points A project has an Earned Value of $ 2700 but should have installed $2100 worth of work by day 24 of the project.

2 points A project has an Earned Value of $ 2700 but should have installed $2100 worth of work by day 24 of the project. Considering that the project is contracted at $4300 for a duration of 60 days, what is the "Time To Complete" if the discrepancy is expected to continue for the rest of the project? Type your