Question: A project has an Earned Value of $ 2 0 0 0 but should have installed $ 3 3 0 0 worth of work by

A project has an Earned Value of $2000 but should have installed $3300 worth of work by day 27 of the project. At this point, the project is 9 days behind schedule. Considering that the project is contracted at $5500 for a duration of 56 days, what is the "Time To Complete" (in days) if the discrepancy is considered an isolated event and the pace is expected to proceed as originally planned?
48
 A project has an Earned Value of $2000 but should have

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!