Question: A project has an Earned Value of $ 2 0 0 0 but should have installed $ 3 3 0 0 worth of work by
A project has an Earned Value of $ but should have installed $ worth of work by day of the project. At this point, the project is days behind schedule. Considering that the project is contracted at $ for a duration of days, what is the "Time To Complete" in days if the discrepancy is considered an isolated event and the pace is expected to proceed as originally planned?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
