Question: 2 : Question 1 5 ( 1 point ) Page 1 5 of 4 0 A project manager decides to purchase insurance to handle the
:
Question point
Page of
A project manager decides to purchase insurance to handle the risks associated with potential damages to equipment during transportation. Which risk response strate is being applied?
Mitigation
Acceptance
Exploitation
Transference
Avoidence