Question: 2 . Question 2 A Product Owner writing a user story needs the story to fit within the planned Sprint. If the user story is
Question
A Product Owner writing a user story needs the story to fit within the planned Sprint. If the user story is too large, they break it down into multiple scaleddown stories to meet which of the I.NVEST story writing criteria?
point
Independent
Negotiable
Valuable
Small
Question
As a Product Owner, you need to add estimates to your Backlog for a small number of items. Youd like your team to reach a consensus on the number of items, and you would also like to incorporate the Fibonacci sequence. Which effort estimation technique should you use?
point
Dot Voting
Affinity Mapping
Planning Poker
The Bucket System
Question
Which of the following is true regarding the factors that determine how long a Sprint should last in the Scrum Methodology?
point
Sprints should always be set for two weeks for the Scrum Team.
The timeline of a Sprint should be short enough to generate a learning cycle.
The stakeholders should decide how long Sprints should be for the team.
Sprints should be as long as possible to allow developers to complete tasks.
Question
Which of the following is a key deliverable of Sprint Planning?
point
The Sprint Backlog
A burndown chart
Retrospective notes
The project charter
Question
What is a main benefit of a Sprint review for all team members working on the project?
point
Team members get to judge others from different teams.
Team members get to collect feedback on each others performance.
Team members can get instant feedback from the team during the demo.
Team members can review the project's remaining tasks.
Question
Fill in the blank: Retrospectives in Scrum happen a traditional project.
point
as often as in
more often than in
less often than in
Question
Fill in the blank: When a team conducts Sprint Planning, they use the average velocity of to determine how many items they can safely add to their Sprint Backlog.
point
at least three weeks
at least three Sprints
at least three days
at least three story points
Question
What is the main benefit of allowing team members to physically move the status of an item between TodoIn Progress, and Done
point
It allows team members to clearly see the flow of a task.
It allows team members to use the status updates in Retrospectives.
It helps Product Owners find the velocity of the team.
It allows team members to track who completes the most points.
Question
Utilizing tools in Scrum helps make the team fully aware of progress and updates. This embodies which Scrum pillar?
point
Adaptation
Inspection
Transparency
Commitment
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock