Question: 2. QUESTION ? Consider the following project network, with task duration data provided (in days). Which of the following is the slack in activity G?

2. QUESTION ? Consider the following project
2. QUESTION ? Consider the following project network, with task duration data provided (in days). Which of the following is the slack in activity G? E Finish 1 Start 2 B 4 G 2 1 2 H 3 0 days 1 day 2 days 3 days 4 days Click Save and Submit to see and submit. Click Save All Answers to saue all answers. Save All Answers