Question: Consider the following project network, with task duration data provided. If H is delayed for 3 days and other tasks are still on schedule, how

Consider the following project network, with task
Consider the following project network, with task duration data provided. If H is delayed for 3 days and other tasks are still on schedule, how many days will this project be delayed? Finish E 7 J 1 A F 1 Start N B UN 1 D 2 H 3 O days 1 day 2 days 3 days 4 days