Question: 2.5 QUESTION Consider the following project network, with task duration data (in days) provided. Which of the following is the completion time for this project?

2.5 QUESTION Consider the following project
2.5 QUESTION Consider the following project network, with task duration data (in days) provided. Which of the following is the completion time for this project? UN A 3 E 2 Start Finish D 3 B 4 9 9000 12 14 None of the above