Question: 2. Suppose a project has 10 activities (Activity A to J). The path A, B, C, D, F, J is 120 days, the path of

 2. Suppose a project has 10 activities (Activity A to J).

2. Suppose a project has 10 activities (Activity A to J). The path A, B, C, D, F, J is 120 days, the path of A, B, C, D, E, J is 150 days and Path A, B, C, D, G, J is 135 days. If the activity E is crashed by 20 days, then the overall duration of the project will decrease by 20 days. (2 marks)