Question: 2. The table below shows the relevant task data for a future design project. Draw in Word (or other software of your choice) a fully

2. The table below shows the relevant task data

2. The table below shows the relevant task data for a future design project. Draw in Word (or other software of your choice) a fully analyzed AON network diagram, for this project; showing all ES, EF, LS and LF times. Develop an Activities Boundary Timetable, identify the critical path, and determine the project duration. Do not use MSP! (15 points) Task Immediate Duration Predecessors (weeks) A 3 B 5 B 3 D B 4 E A, B 6 F A, B 7 G D, E 4 H C, D, E 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!