Question: 2. Using the data below, reduce the project completion time by four days. Assume a linear time-cost trade-off for each task and show, step by

2. Using the data below, reduce the project

2. Using the data below, reduce the project completion time by four days. Assume a linear time-cost trade-off for each task and show, step by step, how you arrived at your schedule. Also indicate the critical path. D,12 B,10 6,7 Start A, E,10 1,6 JO End C,8 H,9 F,14 Activity B Normal Time (days) 10 8 12 10 14 7 9 D E F G H I Normal Cost (S) 100 80 120 100 140 70 90 60 Crash Time (days) 9 7 10 7 12 5 6 5 Crash Cost (S) 110 100 140 120 190 100 150 80 6