Question: 2. Using the data below, reduce the project completion time by four days. Assume a linear time-cost trade-off for each task and show, step by

2. Using the data below, reduce the project

2. Using the data below, reduce the project completion time by four days. Assume a linear time-cost trade-off for each task and show, step by step, how you arrived at your schedule. Also indicate the critical path. 1,12 3,10 6.7 Start A, 5,10 2.0 Activity B D E F G H 1 Normal Time (days) 10 8 12 10 14 7 9 Normal Cost (S) 100 80 120 100 140 70 90 60 Crash Time (days) 9 7 10 7 12 5 6 S Crash Cost (S) 110 100 140 120 190 100 150 80 6