Question: Using the data below, reduce the project completion time by four days. Assume a linear time-cost trade-off for each task and Show, step by step,

Using the data below, reduce the project completion time by four days. Assume a linear time-cost trade-off for each task and Show, step by step, how you arrived at your schedule. Also indicate the critical path. Activity Normal Time Normal Crash Time Crash days Cost '. da s Cost '. 100 110 .- 140 120